ATM_ID: 726D2910-73A2-1014-B6C0-D6A156619FB6 MFF: PLANNEDTIMESTAFF: ID: DPQA_Regression_COPY-PRINT/Testcases/SPAR/R16-08_Test_Cases/83198 TESTCASE_HEADLINE: [SPAR]->CQGbl00972011_2 Once the clear all is pressed after first copy job, Check whether confirmation popup for copy activity report is getting displayed after performing the second copy job GROUP: FEATURE: SUB_FEATURE: INPUT:

  1. Set the system timeout to the value which is greater than minimal value
  2. Make sure that "Copy Activity Report" option is enabled
PROCEDURE:

  1. Place the original in Platen/DADH. Perform a copy job.
  2. After completion of job, check the expected result (1)
  3. Press Clear All button and check the expected result (2)
  4. Perform another copy job.
  5. After completion of job, check the expected result (3)
OUTPUT:

  1. Confirmation popup should display with "Print Copy Activity Report" and "Make More Copies"
  2. Confirmation popup should be closed
  3. Confirmation popup should display with "Print Copy Activity Report" and "Make More Copies"
PROCESS: PRIORITY: TEST_TYPE: LOE: RESOURCE_HW: RESOURCE_CONSUMEABLES: RESOURCE_MEDIA: SKILL_SET: TEST_CASE_TYPE: TESTCASE_SOURCE: SPEC: SPEC_VERSION: SPEC_TAG: Mapping Not Required ATM_OWNER: APPROVE_QE: APPROVED_QE: APPROVE_SE: APPROVED_SE: APPROVE_SPAR: APPROVED_SPAR: ASSOCIATED_TESTCASES: TRAINING: TESTCASE_VERSION: TESTCASE_STATE: TESTCASE_PLATFORM: TESTCASE_PRODUCT: TESTCASE_APPROVALS: CDATE: 1476023209 MDATE: 1476023209 MUSER: w4939RDM AUTHOR: w4939RDM ATM_MCOMMENTS: Imported from CSV HISTORY: ATM_LOCKED: ATM_REQLINK: ATM_REQCOUNT: 0 QA_TEAM: TC_WEIGHTAGE: FILENAME: FILEDESC: FILES: